Back At Sea
Making plans to drop the DOTs and complete one box per day…
FRIDAY, 04.03.09

Coastal Samoa
1624: Job Site ETA
At the current pace (which I expect us to start improving by later tonight), we’ll be at the job site around Monday at 5 p.m. Deep Ocean Transponders (DOTs) should take four to five hours so we’ll be launching between 10 p.m. and midnight on April 6th. If we keep the current boxes, we will finish up A and B a couple weeks later. At one box per day, 14 left.